TRIPLE TRANSPORTER PROJECT
This is one of the challenged and different sequence project. There
are 26 tanks in the project. The process of the project is as
follows: LOAD
à
DECREASING
à WATER RINSE
à ACID DRAIN
à WATER RINSE
à ELECTROPLATING
à WATER RINSE
à ZINC PLATING
à WATER RINSE
à
UNLOAD. In this project, three transporters are working in same time
with co-ordination each other. More safety interlocks are done to
avoid the accidents between the three transporters. When the main
supply power gets "OFF" the three transporters are stop their
current positions and the power will get "ON", after pressing the
start signal the transporters starts from their current positions.
This is used to reduce the cycle time and increase the protection
with 0% defective components. And also provided the current running
feedback display and transporters waiting delay time setting screens
are displayed in HMI.
ARM HOLE MACHINE
To get high accuracy of hole positions, using of Servo amplifier for
job movement and the hole made by drill and reamer fixed in a single
rod. The movement of the drill head is controlled by hydraulic
press. The speed of the spindle is controlled by Mitsubishi VFD. By
the combination of these can get more accuracy holes in a job. Also
provided the servo movement position setting screens and cycle
running feedback displays are displayed in HMI. The total functions
are controller by the PLC.
LEAK TESTING MACHINES
These types of machines are used to find out the leak in a component
by using vacuum pressure. To know the leak value in a component for
segregate quality and unqualified components. Done the communication
with Air Supply Unit (ASU) through RS-232 communication. Read the
leak value from the ASU and done the comparison with set value in
HMI. Finally give the result, the component OK or NOT OK as per the
leak value.
DRY AND WET RECTIFICATION MACHINE USING RFID
This project is based on communication with RFID and bar code
reader. In this project, every ballet contains a single component is
moving through a conveyor. Before reach this rectification machine,
the bar code contains all data with date and time with test results.
When reach the rectification machine, first read the data about the
particular component from the bar code reader through RS-232 /
RS-485 communication between PLC and Bar code reader unit. After
corrected the defective tests, write the data to the data storage
card fixed in a particular ballet contain the component.
|
Drum Brake
Assembly Line |
|
Component |
|
Drum Brake Assembly |
|
Description |
|
This Machine consists of six
stages and is used for assembling of brake assembly. First
stage is Assembling of back plate with wheel cylinder by nut
runner. Unload from first stage reverse the component and
load in second stage. Here shoes are assembled. Stage three
SHD component is loaded and in fourth stage outer diameter
of shoe is aligned. Fifth stage is the inspection by probe
sensing and sixth stage is date code printing. This machine
is operated by pneumatic with PL integration |
|
 |
|
Renault Reservoir
Assembly And joint Leak Testing SPM |
|
Component |
|
Master Cylinder
and Reservoir |
|
operation |
|
Reservoir
Assembly and Joint Leak |
|
Description |
|
This Machine is
used for testing the joint of reservoir and master cylinder
the master cylinder and reservoir assembly is loaded and
plug all the ports and create vacuum in reservoir and check
with fukuda vacuum leak tester. This machine is operated by
pneumatic with PLC integration. Incase the component is
rejected, reservoir and master cylinder can be dismantled in
a fixture |
|
 |
|